• Early Production Facility PLANT: Hydrocarbon Sludge cleaning of High Pressure, Medium Pressure, Low Pressure Separators and (LPW) Separator.
  • Plant-1: Cleaning of Production Separator and Buffer Vessel
  • Plant-1 De Ethanizer Column: Dismantling and Cleaning of (36) trays and column. Re-installation of Column Trays
  • Plant-2: Isolation/De-isolation & Cleaning of Production separators and Buffer Vessel Manifold
  • Plant-2: Isolation/De-isolation & Cleaning of Test Separator
  • Plant-2 De Ethanizer Column: Dismantling and Cleaning of (24) trays and column. Re-installation of Column Trays
  • Plant-3: Cleaning of HP Separator
  • Plant-3: Cleaning of TEST, Medium Pressure, Low Pressure & Flash separators
  • Plant-3: Cleaning of Corrugated Plate Interceptor (CPI) Pit T-302A/304/305

Job was successfully executed in record 07 Days in September 2018 at PPL Adhi Field ATA-18.